RECOMMENDED SEQUENCE OF OPERATIONS UPDATES

Increase the duration of building purge mode / flush mode to increase dilution. Start ventilation mode before occupancy.

Run fresh air systems during nights and weekends.

Run restroom exhaust continuously 24/7. Increase restroom exhaust rates if exhaust and make up system capacity allows.

Monitor and control building humidity. Revise dehumidification and humidification modes and sequences as necessary.

❑ Maintain equal space pressures on all floors in multi-story buildings to avoid cross contamination between different floors. ❑ Maximize supply air reset sequence for buildings equipped with this sequence. This would allow more outdoor air and more air changes within the building.

Disable demand-controlled ventilation and unoccupancy / vacancy sequences during scheduled business hours where possible. Use CO2 sensors for particle measurement only.

Bypass Heat Recovery Systems with enthalpy wheels, where cross contamination cannot be avoided.

Avoid cycling fan coil units on/off. Switch to constant volume operation if needed.