Vista Issue 2--Year End 2025
EDG2 Scales Up with Precision and Speed
Snapshot of what we deployed and tested:
35 Diesel Generator Sets (2,500 kW each) 35 UPS Containers (1,500 kW each) 35 Automated Switchboards (3,000 amp) 35 Maintenance Bypass Switchboards (2,000 amp) 140 Split Unit AC Systems 105 Distribution Switchboards 120 Static Transfer Switches
•
•
•
In just three months, EDG2’s commissioning team delivered an impressive 45 MW of critical power—an achievement that underscores both technical excellence and operational agility. The team swiftly tested and validated the electrical and mechanical infrastructure across five Data Halls spanning two buildings from the moment the client issued the Notice to Proceed. A 7-to-make-6 Catcher System powered each hall. The team designed them to support 9 MW of critical load. These systems are built for resilience, with six Primary Systems and one Reserve System per hall. Each system includes a 2,500 kVA transformer, a 3,000 amp switchboard, a 2,250 kW diesel generator, a 1,500 kW UPS module, four 600 amp Static Transfer Switches (STS), and four 500 kVA Power Distribution Units (PDUs). The team tailored the cooling strategies to each hall’s needs: three halls used Munters SyCool Split Units with Free Cooling, while the other two relied on 500-ton air-cooled chillers paired with Fan Walls. The scale of the commissioning effort was nothing short of extraordinary. This milestone reflects the precision, speed, and scale that define EDG2’s approach to data center commissioning. It’s a testament to the team’s expertise and commitment to delivering world-class infrastructure under tight timelines.
•
•
•
•
120 PDUs
•
528 Starline Busways
•
14 Chillers 50 Fan Walls
•
•
72 SyCool Systems
•
Plus EPMS, MBS, Plant Managers, and IR Scanning
•
Made with FlippingBook flipbook maker